Paragraph 7
Any alternative apparatus to be constructed by the undertakers in pursuance of paragraph 6 above in land held or used, or intended for use, by the nominated undertaker for the purposes of its undertaking under this Act or held by the Secretary of State, or in which the undertakers have obtained the necessary facilities and rights, shall be constructed in such manner, and in such line or situation and in accordance with such programme, as is agreed between the undertakers and the nominated undertaker with a view to securing, among other things, the efficient implementation of the necessary work, the avoidance of unnecessary delay and the continued fulfilment by the undertakers of their service obligations to a standard no less than that achieved prior to the removal of the apparatus which the alternative apparatus replaces, or, in default of agreement, determined by arbitration under paragraph 18 below.
If the undertakers fail to comply with an agreement made under sub-paragraph (1) above, or with the decision of an arbitrator under paragraph 18 below, they shall be liable to compensate the nominated undertaker in respect of any loss or damage (other than loss of, or arising from delayed receipt of, operating revenue due to delayed opening of the rail link) directly resulting from the failure.
Notes on Part II
Modifications
- C1
-
Sch. 15 Pt. II (paras. 1-18) applied (with modifications) (19.2.1999) by S.I. 1999/537, art. 13(1), Sch. 3 paras. 1-8
Sch. 15 Pt. II (paras. 1-18) applied (with modifications) (22.3.2001) by S.I. 2001/1451, art. 15(1), Sch. 3 para. 1(j)
Sch. 15 Pt. II applied (with modifications) (12.8.2002) by S.I. 2002/1943, art. 15(1)(d)