Paragraph 5
In constructing the bridge, or bridges, forming parts of Works Nos. 1AA, 1BB, 1CC, 1DD, 1EE, 3B and 3C over the canal, the nominated undertaker shall ensure that the soffit of any bridge at its lowest point is at a level of not less than 26.28 metres above Ordnance Datum Newlyn.
Notes on Part VI
Textual amendments
- F1
-
Words in heading in Sch. 15 Pt. VI substituted (2.7.2012) by The British Waterways Board (Transfer of Functions) Order 2012 (S.I. 2012/1659), art. 1(2), Sch. 3 para. 14(2) (with arts. 4-6)
Modifications
- C1
-
Sch. 15 Pt. VI (paras. 1-11) applied (with modifications) (22.3.2001) by S.I. 2001/1451, art. 15(1), Sch. 3 paras. 1(j), 3(5)