In constructing the bridge, or bridges, forming parts of Works Nos. 1AA, 1BB, 1CC, 1DD, 1EE, 3B and 3C over the canal, the nominated undertaker shall ensure that the soffit of any bridge at its lowest point is at a level of not less than 26.28 metres above Ordnance Datum Newlyn.