Paragraph 11 Construction environmental management planI1
United Kingdom
No phase of the authorised development may commence until a construction environmental management plan (which must accord with the outline construction environmental management plan) for that phase has been submitted to and approved by the relevant planning authority, in consultation with the relevant highway authority and the Environment Agency.
The construction environmental management plan must include the following documents relevant to the phase of the authorised development in respect of which it is submitted—
site waste management plan;
breeding bird protection plan;
new watercourse crossing inventory; and
upgraded watercourse crossing inventory.
The construction environmental management plan must be implemented as approved.