Paragraph 8 Fencing and other means of enclosureI1
United Kingdom
No phase of the authorised development may commence until written details of all proposed permanent and temporary fences, walls or other means of enclosure of the connection works for that phase have been submitted to and approved by the relevant planning authority as part of the detailed design approval required by requirement 2(1).
For the purposes of requirement 8(1), “commence” includes any site preparation works.
Any construction site must remain securely fenced in accordance with the approved details at all times during construction of the authorised development.
Any temporary fencing must be removed on completion of the phase of construction of the authorised development for which it was used.
Any approved permanent fencing must be completed before completion of the authorised development.