Paragraph 2 Detailed design approvalI1
United Kingdom
No phase of the authorised development may commence until details of—
the layout;
scale;
proposed finished ground levels;
external appearance;
hard surfacing materials;
vehicular and pedestrian access, parking and circulation areas;
refuse or other storage units, signs and lighting;
drainage, water, power and communications cables and pipelines;
programme for landscaping works; and
fencing,
relating to that phase have been submitted to and approved in writing by the relevant planning authority.
The details submitted must accord with—
the location, order limits and grid coordinates plan;
the works plan;
the principles and assessments set out in the environmental statement; and
the outline design principles, or such variation thereof as may be approved by the relevant planning authority pursuant to requirement .
The authorised development must be carried out in accordance with the approved details.
Annotations
Commencement
- I1
Sch. 1 Pt. 2 para. 2 in force at 19.6.2020, see art. 1