  • Work No. 1. A rubble mound breakwater, protected on its external faces by rock armour, commencing at reference point NF 072088 803889, curving for a distance of 150 metres in a generally east-north-easterly direction and then in a generally south-easterly direction and terminating at reference point NF 072227 803857.

  • Work No. 2. A slipway consisting of a reinforced concrete slab over rock fill on the bed of the sea, protected on its south face by rock armour and on its north face by a vertical concrete face, and a timber alignment structure, commencing at reference point NF 072119 803821 extending in a generally easterly direction for a distance of 97 metres and terminating at reference point NF 072216 803811.