Regulation 6 Notification
(1)
A project is notifiable if the construction work on a construction site is scheduled to—
(a)
last longer than 30 working days and have more than 20 workers working simultaneously at any point in the project; or
(b)
exceed 500 person days.
(2)
Where a project is notifiable, the client shall give notice in writing to the Executive as soon as is practicable before the construction phase begins.
(3)
The notice shall—
(a)
contain the particulars specified in Schedule 2;
(b)
be clearly displayed in the construction site office in a comprehensible form where it can be read by any worker engaged in the construction work; and
(c)
if necessary, be periodically updated.