Schedule 7 Places of work requiring inspection
| Column 1 | Column 2 |
|---|---|
| Place of work | Time of Inspection |
1 Any working platform or part thereof or any personal suspension equipment provided pursuant to regulation 6(3)(b) or (c). | 1 (i) Before being taken into use for the first time; and (ii) after any substantial addition, dismantling or other alteration; and (iii) after any event likely to have affected its strength or stability; and (iv) at regular intervals not exceeding 7 days since the last inspection. |
2 Any excavation which is supported pursuant to regulation 12(1), (2) or (3). | 2 (i) Before any person carries out work at the start of every shift; and (ii) after any event likely to have affected the strength or stability of the excavation or any part thereof; and (iii) after any accidental fall of rock or earth or other material. |
3 Cofferdams and caissons | 3 (i) Before any person carries out work at the start of every shift; and (ii) after any event likely to have affected the strength or stability of the cofferdam or caisson or any part thereof. |