Paragraph 16
England and Wales
Where, as a result of F1an environmental permit granted under regulation 13 of F2the Environmental Permitting (England and Wales) Regulations 2016, the enforcing authority is precluded by virtue of section 78YB(4) from specifying in a remediation notice any particular thing by way of remediation which it would otherwise have specified in such a notice,—
the F3environmental permit;
the location and extent of the contaminated land in question, in sufficient detail to enable it to be identified, whether by reference to a plan or otherwise; and
the matters referred to in sub–paragraphs (c), (d) and (e) of paragraph 1.
Annotations
Textual amendments
- F1
Words in Sch. 3 para. 16 substituted (6.4.2010 immediately after S.I. 2009/3381 comes into force) by The Environmental Permitting (England and Wales) Regulations 2010 (S.I. 2010/675), reg. 1(1), Sch. 26 para. 32(3)(a) (with reg. 1(2))
- F2
Words in Sch. 3 para. 16 substituted (1.1.2017) by The Environmental Permitting (England and Wales) Regulations 2016 (S.I. 2016/1154), reg. 1(1), Sch. 29 para. 22(6) (with regs. 1(3), 77-79, Sch. 4)
- F3
Words in Sch. 3 para. 16(a) substituted (6.4.2010 immediately after S.I. 2009/3381 comes into force) by The Environmental Permitting (England and Wales) Regulations 2010 (S.I. 2010/675), reg. 1(1), Sch. 26 para. 32(3)(b) (with reg. 1(2))