Paragraph 2 I1
United Kingdom
In paragraph 1(g)(vii), “declared net capacity” means the capacity of electricity generation of a generating station calculated by A-B, where—
-
“A” means the maximum capacity of electricity generation at which a generating station is able to be operated for a sustained period without damage being caused to it (assuming the source of energy used to generate electricity is available without interruption); and
-
“B” means the amount of electricity that is consumed by the station whilst operating at such maximum capacity.
Annotations
Commencement
- I1
Sch. para. 2 in force at 1.8.2014, see reg. 1