Regulation 11 Individual suppliers' reserve amounts
United Kingdom
An electricity supplier must make a reserve payment to the CFD counterparty in respect of a quarterly obligation period (“the relevant period”) by the 5th working day after the day on which the CFD counterparty has issued a notice to that supplier under regulation 15(3) (notice of reconciliation payment) in the relevant period.
Where a supplier fails to pay all or part of a reserve payment by the date by which it must be paid in accordance with paragraph (1), that supplier must pay the CFD counterparty simple interest on any unpaid amount at the rate specified in regulation 35(1) from the day after the date by which that amount should have been paid.
F2Subject to regulation 14A, the amount of a supplier's reserve payment in respect of the relevant period is the amount given by—
where—
TRA is total reserve amount for that period;
SRE is the amount of electricity supplied by that supplier in the reference period as determined on the date on which that total reserve amount is determined; F4...
F5SXE is the amount of EII excluded electricity supplied by that supplier in the reference period as determined on the date on which that total reserve amount is determined;
RE is the total amount of electricity supplied by all suppliers in the reference period as determined on the date on which that total reserve amount is determined;
F6XE is the total amount of EII excluded electricity supplied by all suppliers in the reference period as determined on the date on which that total reserve amount is determined.
For the purposes of paragraph (3) and regulation 14(4) the amount of electricity supplied by an electricity supplier in a reference period is the amount of all electricity which the BSCCo determines was supplied by that supplier in that period, on the basis of the most recent F9BSC volume allocation run which the BSCCo has carried out.
Annotations
Textual amendments
- F1
Reg. 11(1) substituted (1.10.2017) by The Electricity Supplier Payments (Amendment) Regulations 2017 (S.I. 2017/502), regs. 1(3), 8
- F2
Words in reg. 11(3) inserted (1.7.2017) by The Electricity Supplier Payments (Amendment) Regulations 2017 (S.I. 2017/502), regs. 1(2), 9
- F3
Reg. 11(3) formula substituted (1.4.2015) by The Electricity Supplier Obligations (Amendment & Excluded Electricity) Regulations 2015 (S.I. 2015/721), regs. 1(2), 22(2)(a)
- F4
Word in reg. 11(3) omitted (1.4.2015) by virtue of The Electricity Supplier Obligations (Amendment & Excluded Electricity) Regulations 2015 (S.I. 2015/721), regs. 1(2), 22(2)(b)(i)
- F5
Words in reg. 11(3) inserted (1.4.2015) by The Electricity Supplier Obligations (Amendment & Excluded Electricity) Regulations 2015 (S.I. 2015/721), regs. 1(2), 22(2)(b)(ii)
- F6
Words in reg. 11(3) inserted (1.4.2015) by The Electricity Supplier Obligations (Amendment & Excluded Electricity) Regulations 2015 (S.I. 2015/721), regs. 1(2), 22(2)(c)
- F7
Words in reg. 11(4) omitted (1.4.2015) by virtue of The Electricity Supplier Obligations (Amendment & Excluded Electricity) Regulations 2015 (S.I. 2015/721), regs. 1(2), 22(3)
- F8
Words in reg. 11(4) inserted (1.4.2016) by The Electricity Supplier Payments (Amendment) Regulations 2016 (S.I. 2016/363), regs. 1(3), 7(2)
- F9
Words in reg. 11(5) substituted (1.4.2015) by The Electricity Supplier Obligations (Amendment & Excluded Electricity) Regulations 2015 (S.I. 2015/721), regs. 1(2), 22(4)