Regulation 9 Notification of work with asbestosF1I1
Northern Ireland
Subject to regulation 3(2), an employer shall not undertake any work with asbestos unless he has notified the appropriate office of the enforcing authority in writing of the particulars specified in Schedule 1 at least 14 days before commencing that work or such shorter time before as the enforcing authority may agree.
Where an employer has notified work in accordance with paragraph (1) and there is a material change in that work which might affect the particulars so notified (including the cessation of the work), the employer shall forthwith notify the appropriate office of the enforcing authority in writing of that change.
Annotations
Textual amendments
- F1
Regulations revoked with savings (28.5.2012) by The Control of Asbestos Regulations (Northern Ireland) 2012 (S.R. 2012/179), reg. 33(1) (with regs. 3(5), 33(3))