Paragraph 14 ArchaeologyI1

England, Wales and Scotland

(1)

No part of the authorised development is to commence until a written scheme of archaeological investigation which must include, as a minimum, the archaeological mitigation measures set out in the environmental mitigation schedule has been submitted to and approved by the local planning authority.

(2)

The authorised development must be carried out at all times in accordance with the scheme approved under sub-paragraph (1).

(3)

Any archaeological remains not previously identified which are revealed when carrying out the authorised development must be retained in place and reported to the local planning authority in writing within 3 working days.

(4)

No construction operations are to take place within 10 metres of such remains for a period of 14 days from the date of such notification unless otherwise agreed by the local planning authority.

(5)

If the local planning authority is of the view that the archaeological remains require further investigation, no construction operations are to take place within 10 metres of the remains until provision has been made for the investigation and recording of the remains in accordance with details first submitted in writing to, and approved by, the local planning authority.

Annotations

Commencement

I1

Sch. 2 para. 14 in force at 26.2.2015, see art. 1

Notes on the whole SI

Textual amendments

F1

Words in Preamble inserted (13.2.2015) by The Cornwall Council (A30 Temple to Higher Carblake Improvement) (Correction) Order 2015 (S.I. 2015/243), arts. 1, 2(2)