Only when impact driven or part-driven pile foundations or detonation of explosives are proposed to be used as part of the foundation installation, the undertaker must provide the following information to the Marine Noise Registry (MNR)—

(a)

prior to the commencement of the licensed activities, information on the expected location, start and end dates of impact pile driving/detonation of explosives to satisfy the Marine Noise Registry’s Forward Look requirements; and

(b)

within 12 weeks of completion of impact pile driving/detonation of explosives, information on the exact locations and specific dates of impact pile driving/detonation of explosives to satisfy the Marine Noise Registry’s Close Out requirements.

(2)

The undertaker must notify the MMO of the successful submission of Forward Look requirements.