Paragraph 20 Submission and approval of plansI1
England and Wales
Before the beginning to construct any specified work, the undertaker must submit to the Agency for approval plans of the specified work and such further particulars available to it as the Agency may within 28 days of the receipt of the plans reasonably request.
Any such specified work must not be constructed except in accordance with such plans as may be approved in writing by the Agency, or determined under paragraph 32.
Any approval of the Agency required under this paragraph—
must not be unreasonably withheld or delayed;
is deemed to have been refused if it is neither given nor refused within two months of the submission of the plans or such later date as is agreed between the Agency and the undertaker and if further particulars have been requested pursuant to sub-paragraph (1) the period between the making of this request and the provision of further particulars in response to it will not be taken into account in the calculation of the two months for the purposes of this sub-paragraph (b);
may be given subject to such reasonable requirements as the Agency may have for the protection of any drainage work or the fishery or for the protection of water resources, or for the prevention of flooding or pollution or for nature conservation or the prevention of environmental harm in the discharge of its environmental duties.
The Agency must use its reasonable endeavours to respond to the submission of any plans before the expiration of the period mentioned in sub-paragraph (3)(b).
In the case of a refusal, the Agency must provide reasons for the grounds of that refusal.