Paragraph 23 Timing of works and service of noticesI1
England and Wales
Subject to sub-paragraph (2), any specified work, and all protective works required by the Agency under paragraph 22, must be constructed—
without unreasonable delay in accordance with the plans approved under this Part of this Schedule; and
to the reasonable satisfaction of the Agency,
and the Agency is entitled by its officer to watch and inspect the construction of such works.
The undertaker must give to the Agency not less than fourteen days’ notice in writing of its intention to begin construction of any specified work and notice in writing of its completion not later than seven days after the date on which it is completed.
If the Agency reasonably requires, the undertaker must construct all or part of the protective works so that they are in place prior to the construction of any specified work to which the protective works relate.