Paragraph 77 ConsultationI1
England and Wales
The undertaker must consult with the PLA on draft documentation, prior to the submission of any plan, scheme or strategy under requirements 7 (code of construction practice), 10 (emergency preparedness and response plan), 11 (lighting strategy), 16 (jetty works environmental design scheme) and 23 (decommissioning environmental management plan) which relate to Work No. 4, to the relevant planning authority.
The undertaker must consult with the PLA on any updates to a plan, scheme or strategy approved under requirements 7 (code of construction practice), 10 (emergency preparedness and response plan), 11 (lighting strategy), 16 (jetty works environmental design scheme) and 23 (decommissioning environmental management plan) which relate to Work No. 4, prior to submission to the relevant planning authority under requirement 3 (approved details and amendments to them).
Annotations
Commencement
- I1
Sch. 12 para. 77 in force at 27.11.2025, see art. 1