Paragraph 14 Operational environmental management planI1
England and Wales As made
No part of Work No. 1 may be fully commissioned until a written operational environmental management plan for that part has been submitted to and approved by the relevant planning authority in writing.
The operational environmental management plan must include details of proposed operational maintenance procedures, security arrangements and the following items set out in the mitigation schedule—
paragraphs (c), (e) and the matters listed under additional mitigation of item 1.12;
items 3.17 (b) and (e);
item 4.19 (f);
the first paragraph of item 7.9;
item 12.3; and
item 14.8.
Any operational environmental management plan approved under sub-paragraph (1) must be implemented and maintained throughout the operation of the relevant part of Work No. 1 to which the plan relates.