Part 2 SUBSTITUTE AND SUPPLEMENTARY DOCUMENTSI1
England and Wales
(1) Originating Document | (2) Replacement or supplementary part | (3) Document reference | (4) Date | (5) Examination library reference |
|---|---|---|---|---|
| Environmental statement | Chapter 4: Scheme Description | EX1/C6.2.4_A | October 2023 | [REP-012] |
| Environmental Statement | Chapter 7: Climate Change | EX1/C6.2.7_A | October 2023 | [REP-014] |
| Environmental Statement | Chapter 8: Landscape and Visual Impact | EX2/C6.2.8_A | November 2023 | F1[REP2-008] |
| Environmental Statement | Chapter 19: Soils and Agriculture | EX1/C6.2.19_A | October 2023 | [REP-010] |
| Environmental Statement | Chapter 23: Summary of Significant Effects | EX2/C6.2.23_A | November 2023 | [REP2-010] |
| F2. . . | . . . | . . . | . . . | . . . |
| Environmental Statement | Appendix 14.1: Transport Assessment | EX5s/C6.3.14.1_C | February 2024 | [REP5-014] |
| Environmental Statement | Volume 4: Non-Technical Summary | EX4/C6.5_C | January 2024 | [REP4-033] |
| Environmental Statement | Technical Note on Horizontal Directional Drilling and Cabling under the River Trent | EX5/C8.2.13 | February 2024 | [REP5-034] |
| Environmental Statement | ES Addendum 9.1: Ecology and Biodiversity | EX4/C8.4.9.1 | December 2023 | [REP4-067] |
| Environmental Statement | ES Addendum: Chapter 10:, Hydrology, Flood Risk and Drainage | EX1/C8.4.10.1 | October 2023 | [REP-076] |
| Environmental Statement | ES Addendum: Chapter 10: Hydrology, Flood Risk and Drainage Appendix C8.4.10.2: FRA Sequential and Exception Test | EX3/C8.4.10.2 | December 2023 | [REP3-048] |
| Environmental Statement | ES Addendum: Chapter 13: Archaeological Trial Trenching Evaluation Fieldwork Report for the Shared Cable Corridor | EX3/C8.4.13.1 | December 2023 | [REP3-049] |
| Environmental Statement | ES Addendum: Chapter 13: Additional Archaeological Trial Trenching Interim Report | EX5/C8.4.13.2 | February 2024 | [REP5-048] |
| Environmental Statement | ES Addendum: Appendix 16.1: Solar Photovoltaic Glint and Glare Study | EX1/C8.4.16.1 | October 2023 | [REP-077] |
| Environmental Statement | ES Addendum: 21.1: Human Health and Wellbeing Effects | EX4/C8.4.21.1 | January 2024 | [REP4-068] |
| Environmental Statement | ES Addendum: 21.2: Blyton Park Driving Centre | EX4/C8.4.21.2 | January 2024 | [REP4-069] |
| Environmental Statement | ES Addendum: Updated Air Quality Impact Assessment of a Solar Panel Fire Incident | EX1/C8.4.17.1 | August 2023 | [REP-078] |
| Environmental Statement | ES Addendum: Air Quality Impact Assessment of Battery Energy Storage Systems (BESS) Fire | EX2/C8.4.17.2_A | November 2023 | [REP2-071] |
| Environmental Statement | ES Addendum: Cumulative Effects | EX5/C8.4.23.1 | February 2024 | [REP5-051] |
| Environmental Statement | Technical Note on Cumulative Effects of Additional Schemes | EX4/C8.2.11 | January 2024 | [REP4-059] |
| Environmental Statement | Joint Report on Interrelationships between Nationally Significant Infrastructure Projects | EX4/C8.1.8_D | February 2024 | [REP5-025] |
Annotations
Textual amendments
- F1
Word in Sch. 13 Pt. 2 substituted (26.11.2024) by The Cottam Solar Project (Correction) Order 2024 (S.I. 2024/1222), art. 1, Sch.
- F2
Words in Sch. 13 Pt. 2 omitted (26.11.2024) by The Cottam Solar Project (Correction) Order 2024 (S.I. 2024/1222), art. 1, Sch.
Commencement
- I1
Sch. 13 Pt. 2 in force at 27.9.2024, see art. 1