Paragraph 142 I1

England and Wales

(1)

The undertaker may not under the powers of this Order carry out any specified works without the consent of Gate Burton, which F1must not be unreasonably withheld or delayed but which may be made subject to reasonable conditions and if Gate Burton does not respond within 28 days of the undertaker’s request for consent, then consent is deemed to be given.

(2)

Subject to obtaining consent pursuant to sub-paragraph (1) and before beginning to construct any specified works, the undertaker must submit plans of the specified works to Gate Burton and must submit any such further particulars available to it that Gate Burton may reasonably require.

(3)

Any specified works must be constructed without unreasonable delay in accordance with the plans approved in writing by Gate Burton.

(4)

Any approval of Gate Burton required under this paragraph may be made subject to such reasonable conditions as may be required for the protection or alteration of any apparatus (including proposed apparatus) in the Gate Burton Work No. 4B Area or for securing access to such apparatus or the Gate Burton Work No. 4B Area.

(5)

Where Gate Burton requires any protective works to be carried out either by themselves or by the undertaker (whether of a temporary or permanent nature) such protective works must be carried out to Gate Burton’s reasonable satisfaction.

(6)

Nothing in this paragraph precludes the undertaker from submitting at any time or from time to time, but in no case less than 28 days before commencing the execution of any specified works, new plans instead of the plans previously submitted, and the provisions of this paragraph apply to and in respect of the new plans.

Annotations

Textual amendments

F1

Word in Sch. 15 para. 142(1) substituted (26.11.2024) by The Cottam Solar Project (Correction) Order 2024 (S.I. 2024/1222), art. 1, Sch.

Commencement

I1

Sch. 15 para. 142 in force at 27.9.2024, see art. 1