Paragraph 253 I1
England and Wales
The undertaker may not submit for approval by the relevant planning authorities written details for that part of Work No. 1C in the restricted land in accordance with requirement 5(1) (detailed design approval) without first confirming to the Company whether the undertaker intends to carry out the restricted works.
If the undertaker confirms to the Company that it will carry out the restricted works, and unless a shorter period is otherwise agreed in writing between the undertaker and the Company, not less than 8 weeks before commencing any restricted works, the undertaker must submit to the Company the works details.
No restricted works are to be commenced until the works details in respect of those works submitted under sub-paragraph (2) have been approved by the Company.
Any approval of the Company required under this sub-paragraph (3) F1must not be unreasonably withheld or delayed but may be given subject to such reasonable requirements as the Company may require to be made for the safe use of the Blyton Park Driving Centre operations and in accordance with the Automotive Research and Development Centre planning permission.
Any approval of the Company required under sub-paragraph (3) including any reasonable requirements required by the Company under sub-paragraph (4), must be made in writing within a period of 4 weeks (unless a shorter period is otherwise agreed in writing between the undertaker and the Company) beginning with the date on which the works details were submitted to the Company under sub-paragraph (2).
Work No. 1C must be executed on the restricted land only in accordance with the works details approved by the Company under sub-paragraph (3) including any reasonable requirements notified to the undertaker in accordance with sub-paragraph (4) and the Company is entitled to watch and inspect the execution of those works, subject to it having the necessary property interests in the restricted land to do so.
Nothing in this paragraph precludes the undertaker from submitting at any time or from time to time, but (unless otherwise agreed in writing between the undertaker and the Company) in no case less than 8 weeks before commencing the execution of any restricted works, new works details, instead of the works details previously submitted, and having done so the provisions of this Part of this Schedule apply to and in respect of the new works details.
Annotations
Textual amendments
- F1
Word in Sch. 15 para. 253(4) substituted (26.11.2024) by The Cottam Solar Project (Correction) Order 2024 (S.I. 2024/1222), art. 1, Sch.
Commencement
- I1
Sch. 15 para. 253 in force at 27.9.2024, see art. 1