Paragraph 94 I1
England and Wales
Before beginning to construct any specified work, the undertaker must submit to the Board plans of the specified work, evidence to support said plans and any such further particulars available to it as the Board may within 28 days of the submission of the plans reasonably require (or submission of further particulars if required by the Board).
Any such specified work may not be constructed except in accordance with such plans as may be approved in writing by the Board or determined under paragraph 101.
Any approval of the Board required under this paragraph—
F1must not be unreasonably withheld or delayed;
is deemed to have been given if it is neither given nor refused within 2 months of the submission of the plans for approval (or the submission of further particulars if applicable) or, in the case of a refusal, if it is not accompanied by a statement of the grounds of refusal; and
may be given subject to such reasonable requirements and conditions as the Board may consider appropriate.
The Board must use its reasonable endeavours to respond to the submission of any plans before the expiration of the period mentioned in sub-paragraph (3).
Annotations
Textual amendments
- F1
Word in Sch. 15 para. 94(3)(a) substituted (26.11.2024) by The Cottam Solar Project (Correction) Order 2024 (S.I. 2024/1222), art. 1, Sch.
Commencement
- I1
Sch. 15 para. 94 in force at 27.9.2024, see art. 1