Paragraph 12 ArchaeologyI1
England and Wales
The authorised development may not commence until—
a scheme of additional trial trenching has been submitted to and approved by each relevant planning authority, in consultation with Historic England
additional trial trenching has been carried out in accordance with the scheme approved under sub-paragraph (a); and
updates are made to the Written Scheme of Investigation to account for the results of the additional trial trenching carried out, and the updated Written Scheme of Investigation is submitted to and approved in writing by each relevant planning authority, in consultation with Historic England
The authorised development must be implemented in accordance with the updated Written Scheme of Investigation approved under sub-paragraph 1(c), and any archaeological works must be carried out by a suitably qualified and competent person or body previously notified to each relevant planning authority.
Annotations
Commencement
- I1
Sch. 2 para. 12 in force at 27.9.2024, see art. 1