Part 3 CAPITAL ACTIVITIESI1
England and Wales
| Column 1 | Column 2 | Column 3 | ||
|---|---|---|---|---|
| Activity name | Description | Maximum payment rate | ||
| 1. Access and engagement | ||||
| (a) | Access capital items | Construction of capital items (e.g. gates) to facilitate public access | Up to 100% of actual cost | |
| (b) | Countryside Educational Access Visits Accreditation | Accredited training to carry out educational access visits | £175 once per agreement | |
| 2. Boundaries | ||||
| (a) | Stone-faced bank repair | Repair of stone-faced banks | £31 per m | |
| (b) | Stone-faced bank restoration | Restoration of stone-faced banks | £86 per m | |
| (c) | Earth bank creation | Creation of earth banks | £13.50 per m | |
| (d) | Earth bank restoration | Restoration of earth banks | £7 per m | |
| (e) | Hedgerow laying | Laying of hedgerows | £9.40 per m | |
| (f) | Hedgerow coppicing | Coppicing of hedgerows | £4 per m | |
| (g) | Hedgerow gapping-up | Planting up gaps to create a continuous hedgerow | £9.50 per m | |
| (h) | Hedgerow supplement - casting up | Restoration of hedgerow earth banks | £3 per m | |
| (i) | Hedgerow supplement – substantial pre-work | Restoration of hedgerow where substantial extra work is required | £4.10 per m | |
| (j) | Hedgerow supplement – top binding and staking | Strengthening laid hedges by top binding and staking | £3.40 per m | |
| (k) | Planting new hedges | Planting new hedges | £11.60 per m | |
| (l) | Stone wall restoration | Restoration of stone walls | £25 per m | |
| (m) | Top wiring - stone wall | Restoration of stone walls with top wiring | £3.60 per m | |
| (n) | Stone wall supplement – stone from quarry | Restoration of stone walls where there is insufficient re-usable stone on farm | £44 per m | |
| (o) | Stone wall supplement – difficult sites/m | Restoration of stone walls on particularly difficult sites | £7.90 per m | |
| 3. Feature management | ||||
| (a) | Management of geodiversity features | Management of sensitive geological features | Up to 100% of actual costs | |
| (b) | Major preparatory works for Priority Habitat (creation and restoration) and for Priority Species | Major preparatory works for Priority Habitat (creation and restoration) and for Priority Species | Up to 100% of actual costs | |
| 4. Fencing and gates | ||||
| (a) | Fencing | Installation of fencing | £4.00 per m | |
| (b) | Sheep netting | Installation of sheep netting | £4.90 per m | |
| (c) | Permanent electric fencing | Installation of permanent electric fencing | £4.90 per m | |
| (d) | Rabbit fencing supplement | Installation of rabbit fencing | £2.50 per m | |
| (e) | Fencing supplement - difficult sites | Installation of fencing in difficult sites | £1.24 per m | |
| (f) | Anti-predator combination fencing | Installation of permanent anti-predator combination fencing | £11.10 per m | |
| (g) | Anti-predator temporary electric fencing | Installation of temporary electric anti-predator fencing | £2.85 per m | |
| (h) | Deer fencing | Installation of permanent deer fencing in woodland | £7.20 per m | |
| (i) | Temporary deer fencing | Installation of temporary deer fencing in woodland | £5.20 per m | |
| (j) | Deer exclosure plot | Erection of a deer exclosure plot to protect areas of woodland | £136 per unit | |
| F1(ja) | Deer pedestrian gate | Installation of deer pedestrian gate | £271.50 per unit | |
| (jb) | Deer vehicle gate | Installation of deer vehicle gate | £344.60 per unit | |
| (k) | Wooden field gate | Installation of wooden field gates | £390 per gate | |
| (l) | Stone gate post | Installation of stone gate posts | £280 per post | |
| (m) | Badger gate | Installation of badger gates | £135 per gate | |
| (n) | Water gates | Installation of gates across rivers or streams to prevent livestock access | £240 per gate | |
| F24A. Forestry | ||||
| (a) | Deer high seat | Installation of a temporary vantage point to cull deer | £300 per unit | |
| (b) | Woodland infrastructure | Construction of infrastructure to improve vehicle access to woodland | 40% of actual costs | |
| 5. Historic environment and landscape | ||||
| (a) | Historic and archaeological feature protection | Protection of historic and archaeological features | Up to 100% of actual costs | |
| (b) | Historic building restoration | Restoration of historic buildings in rural areas | Up to 80% of actual costs | |
| (c) | Removal of eyesore | Removal of eyesores | £290 per item | |
| 6. Livestock | ||||
| (a) | Cattle grid | Installation of cattle grids | £835 per item | |
| (b) | Livestock handling facilities | Installation of livestock handling facilities | Up to 80% of actual costs | |
| (c) | Hard bases for livestock drinkers | Construction of a hard base for livestock when drinking | £110 per base | |
| (d) | Hard bases for livestock feeders | Construction of a hard base for livestock when feeding | £170 per base | |
| (e) | Pasture pumps and associated pipework | Installation of pasture pumps and associated pipework | £220 per pump | |
| (f) | Ram pumps and associated pipework | Installation of ram pumps and associated pipework | £1,480 per pump | |
| (g) | Livestock troughs | Installation of livestock drinking troughs | £110 per trough | |
| (h) | Pipework associated with livestock troughs | Installation of pipework for livestock drinking troughs | £2.65 per m | |
| 7. Payment for advice | ||||
| (a) | Implementation Plan | Production of a detailed plan to meet the requirements of another activity in this Schedule | £1,100 per plan | |
| (b) | Feasibility study | Inform the protection or management of habitats, features or species by providing sufficient information to plan and prescribe management over the length of a multi-annual agreement. | Up to 100% of actual costs | |
| (c) | Woodland management plan | Production of a 10 year management plan for woodland | First 100 ha - £20 per ha (minimum payment £1,000) | |
| Over 100 ha - £10 per ha | ||||
| 8. Scrub, tree and bracken control | ||||
| (a) | Scrub control & felling diseased trees | Control or management of scrub, and removal of diseased or immature trees | Payments range from £260 to £1680 per ha subject to site conditions and method of removal. | |
| (b) | Scrub control – difficult sites | Control of scrub on difficult sites | Up to 80% of actual costs | |
| (c) | Tree removal | Tree removal | £144 per tree | |
| (d) | Chemical bracken control | Removal or reduction of bracken by the application of chemicals | £170 per ha | |
| (e) | Mechanical bracken control | Removal or reduction of bracken by mechanical means | £169 per ha | |
| (f) | Rhododendron control | Destruction of rhododendron in a target area | Payments range from £2,800 to £4,400 per hectare subject to site conditions. | |
| 9. Soil and water | ||||
| (a) | Resurfacing of gateways | Resurfacing of gateways | £92 per gateway | |
| (b) | Gateway relocation | Relocation of gateways to prevent water run off | £340 per gateway | |
| (c) | Watercourse crossings | Construction of watercourse crossing for livestock and machinery | £300 per crossing | |
| (d) | Livestock and machinery hardcore tracks | Construction of hardcore tracks for livestock and machinery | £33 per m | |
| (e) | Cross drains | Installation of cross drains under farm tracks or yard | £245 per drain | |
| (f) | Installation of piped culverts in ditches | Installation of piped culverts in ditches/unit | £340 per culvert | |
| (g) | Sediment ponds and traps | Creation of sediment ponds and/or traps | £10 per sq m | |
| (h) | Constructed wetlands for the treatment of pollution | Construction and maintenance of a wetland area to treat polluted water | 50% of costs | |
| (i) | Earth banks and soil bunds | Creation of earth banks and/or soil bunds | £155 for each unit (100m of bund) | |
| (j) | Silt filtration dams or seepage barriers | Creation of silt filtration dams and/or seepage barriers | £75 per unit | |
| (k) | Swales | Creation of swales | £5.95 per sq m | |
| (l) | Check dams | Construction of check dams or woody debris dams in woodland | £42 per dam | |
| (m) | Yard – underground drainage pipework | Installation of underground drainage pipework for yards | £5.50 per m | |
| (n) | Yard inspection pit | Construction of yard inspection pits | £200 per unit | |
| (o) | Concrete yard renewal | Construction of concrete yard with improved or upgraded drainage | £27.14 per sq m | |
| (p) | Rainwater goods | Installation of new guttering and downpipes on existing farmyard buildings | £11.40 per m | |
| (q) | Storage tanks underground | Installation of underground rainwater storage tanks | £350 per cubic metre (“cu m”) | |
| (r) | Above ground tanks | Installation of above ground rainwater storage tanks | £100 per cu m | |
| (s) | First flush rainwater diverters/downpipe filters | Installation of rainwater diverters and filters | £125 per unit | |
| (t) | Relocation of sheep dips and pens | Relocation of sheep dips and pens | £3,675 per unit | |
| (u) | Relocation of sheep pens only | Relocation of sheep pens only | £1,830 per unit | |
| (v) | Sheep dip drainage aprons and sumps | Design and installation of sheep dip drainage aprons and sumps | £18.25 per sq m | |
| (w) | Installation of livestock drinking troughs (in draining pens for freshly dipped sheep) | Installation of livestock drinking troughs in draining pens for freshly dipped sheep | £68 per unit | |
| (x) | Lined biobed plus pesticide loading and washdown area | Installation of a lined biobed plus pesticide loading and washdown area | £118 per sq m | |
| (y) | Lined biobed with existing washdown area | Installation of a line biobed with an existing washdown area | £77 per sq m | |
| (z) | Biofilters/unit | Installation of biofilters | £990 per unit | |
| (aa) | Sprayer or applicator load and washdown area | Installation of a sprayer or applicator load and washdown area | £40 per sq m | |
| (ab) | Roofing (sprayer washdown area, manure storage area, livestock gathering area, slurry stores, silage stores) | Installation of roofing for sprayer washdown areas, manure storage areas, livestock gathering areas, slurry and silage stores. | £62 per sq m | |
| (ac) | Self-supporting covers for slurry F3and anaerobic digestate stores | Installation of self-supporting covers for slurry and anaerobic digestate stores | £30.50 per sq m | |
| (ad) | Floating covers for slurry F4and anaerobic digestate stores and lagoons) | Installation of floating covers for slurry and anaerobic digestate stores and lagoons | £5.60 per sq m | |
| (ae) | Equipment to disrupt tramlines in arable areas | Purchase of equipment to loosen soil in tramline area | £1,500 per machine | |
| (af) | Small leaky woody dams | Creation of small leaky woody dams (between 1m and 2.99m) | £461.39 per dam | |
| (ag) | Large leaky woody dams | Creation of large leaky woody dams (between 3m and 5m) | £764.42 per dam | |
| 10. Trees and orchards | ||||
| (a) | Planting standard hedgerow tree | Planting of standard hedgerow trees | £8.80 per tree | |
| (b) | Planting standard parkland tree | Planting of standard parkland trees | £24.50 per tree | |
| (c) | Planting fruit trees | Planting of fruit trees | £22.50 per tree | |
| (d) | Supply and plant tree | Supply and plant trees | £1.28 per tree | |
| (e) | Supplement for use of individual tree-shelters | Installation of individual tree-shelters after planting | £1.60 per unit | |
| (f) | Tree guard (tube and mesh) | Installation of tree guards (tube and mesh) | £4 per guard | |
| (g) | Tree guard (wood post and rail) | Installation of tree guards (wood post and rail) | £59.50 per guard | |
| (h) | Tree guard (wood post and wire) | Installation of tree guards (wood post and wire) | £84 per guard | |
| (i) | Parkland tree guard – welded steel | Installation of welded steel tree guards | £170 per tree | |
| (j) | Coppicing bankside trees | Coppicing of trees along watercourses | £52 per tree | |
| (k) | Tree surgery | Tree surgery | £96.50 per tree when cutting limbs up to and including 20 centimetres (“cm”) in diameter | |
| £200 per tree when cutting limbs over 20cm in diameter | ||||
| (l) | Stump grinding | Stump grinding | £24 per stump | |
| (m) | Creation of dead wood habitat on trees | Creation of dead wood habitat on trees | £175 per tree | |
| (n) | Identification of orchard fruit tree varieties | Identification of orchard fruit tree varieties | £29 per variety | |
| 11. Wetlands | ||||
| (a) | Grip blocking drainage channels | Installation of grip-blocking drainage channels | £14.80 per block | |
| (b) | Creation of scrapes and gutters | Creation of scrapes or gutters | £2.80 per sq m | |
| (c) | Ditch, dyke and rhine restoration | Restoration of ditches, dykes or rhines | £7.30 per m | |
| (d) | Ditch, dyke and rhine creation | Creation of ditches, dykes or rhines | £8.40 per m | |
| (e) | Pond management – first 100 sq m | Creation or restoration of ponds with an area of less than 100 sq m | £270 per pond | |
| (f) | Pond management – areas more than 100 sq m | Creation or restoration of ponds with an area of at least 100 sq m | £170 per 100 sq m | |
| (g) | Restoration of large water bodies | Restoration of large water bodies | Up to 100% of actual costs | |
| (h) | Timber sluice | Installation of timber sluices | £315 per sluice | |
| (i) | Brick, stone or concrete sluice | Installation of brick, stone or concrete sluices | £2,480 per sluice | |
| (j) | Construction of water penning structures | Construction of water penning structures | Up to 100% of actual costs | |
| 12. Wildlife boxes | ||||
| (a) | Small wildlife box | Installation of a small wildlife box | £28.50 per box | |
| (b) | Medium wildlife box | Installation of a medium wildlife box | £39 per box | |
| (c) | Large wildlife box | Installation of a large wildlife box | £100 per box | |
| F513. Air quality | ||||
| (a) | Automatic slurry scraper | Installation of automatic slurry scraper | £2760 per unit | |
| (b) | Low ammonia emission flooring for livestock buildings | Installation of low ammonia emission flooring for livestock buildings | £72 per sq m | |
Annotations
Textual amendments
- F1
Words in Sch. Pt. 3 inserted (8.2.2021) by The Countryside Stewardship (England) (Amendment) Regulations 2021 (S.I. 2021/42), regs. 1(1), 2(5)(b)(i)
- F2
Words in Sch. Pt. 3 substituted (8.2.2021) by The Countryside Stewardship (England) (Amendment) Regulations 2021 (S.I. 2021/42), regs. 1(1), 2(5)(b)(ii)
- F3
Words in Sch. Pt. 3 inserted (8.2.2021) by The Countryside Stewardship (England) (Amendment) Regulations 2021 (S.I. 2021/42), regs. 1(1), 2(5)(b)(iii)(aa)
- F4
Words in Sch. Pt. 3 inserted (8.2.2021) by The Countryside Stewardship (England) (Amendment) Regulations 2021 (S.I. 2021/42), regs. 1(1), 2(5)(b)(iii)(bb)
- F5
Words in Sch. Pt. 3 inserted (8.2.2021) by The Countryside Stewardship (England) (Amendment) Regulations 2021 (S.I. 2021/42), regs. 1(1), 2(5)(b)(iv)
Commencement
- I1
Sch. Pt. 3 in force at 11.2.2020, see reg. 1(1)