Rule 17 Computation of time
Northern Ireland
Without prejudice to section 39 of the Interpretation Act (Northern Ireland) 1954f1—
where anything is required by these Orders to be done within a specified period of or after the happening of a particular event, the period shall be computed from the end of the day on which the event happens unless the period is expressed to be inclusive of such day;
where anything is required by these Orders to be done within a period not exceeding three days or where a period not exceeding three days is required by these Orders to elapse between the doing of an act and the happening of a particular event, no Saturday or Sunday nor any day on which the Office is closed shall be included in the computation of that period;
where the time prescribed for doing any act expired on a Saturday or a Sunday or any day on which the Office is closed, the act shall be in time if done on the next day on which the Office is open.