Paragraph 23 Un-metered transport supply: gasF1
(1)
Sub-paragraph (2) applies where—
(a)
A has consumed gas for the purposes of transport; and
(b)
part of that supply so consumed was not measured by a meter of any sort (“un-metered gas transport supply”).
(2)
Where this sub-paragraph applies, A may decide that un-metered gas transport supply during a phase is not consumed for the purposes of transport.
(3)
A decision made under sub-paragraph (2)—
(a)
may be made in respect of a phase where such a decision is made on or before the participant submits its first annual report for that phase;
(b)
must not be altered during the phase.
Annotations
Textual amendments
- F1
Order revoked (with savings) (1.10.2018) by The CRC Energy Efficiency Scheme (Revocation and Savings) Order 2018 (S.I. 2018/841), arts. 1, 3