Schedule 2 ACQUISITION OF CERTAIN LANDS FOR ANCILLARY WORKSI1
England, Wales and Scotland
(1) Area | (2) Number of land shown on the land plan | (3) Purpose for which land may be acquired or used |
|---|---|---|
| Districts of Three Rivers and Watford | 12, 13, 18, 20, 45, 46, 48, 49, 52 and 62 | Working site and diversion of utility apparatus |
| District of Watford | 61 and 61a | Working site and afterwards station car park |
| 68 | Substation, working site and access | |
| 76 | Hard landscaping and provision of cycle storage facilities | |
| 87a | Flood compensation | |
| 90 and 91 | Drainage works | |
| 93 | The provision and renewal of rail systems for operational purposes | |
| 99, 100, 102, 103, 104, 105, 106, 107, 110, 112, 114, 116, 118, 120, 120a, 121, 122, 122a, 127, 128, 129 and 130 | The provision and renewal of rail systems and facilities for operational purposes including the installation of a fourth rail power supply, platform extensions at Watford High Street and Watford Junction stations, reconfiguration of permanent way at Watford Junction station and the provision of signalling and traction power equipment |
Annotations
Commencement
- I1
Sch. 2 in force at 21.8.2013, see art. 1