OpenLegislation

Paragraph 24 I1

England, Wales and Scotland

A specified work shall be constructed (and in the case of any temporary work removed) only in accordance with—

(a)

the plans submitted as aforesaid (and, in the case of plans relating to sewers approved, deemed to have been approved or settled by arbitration, as amended from time to time by agreement between DLRL and the specified undertaker); and

(b)

all reasonable requirements made by the specified undertaker for the alteration, or otherwise for the protection, of the apparatus, or for securing access thereto;

and the specified undertaker shall be entitled by its officer to watch and inspect the carrying out of the work.

Annotations

Commencement

I1

Sch. 13 para. 24 in force at 25.11.2005, see art. 1