Paragraph 27
In the assessment of any sums payable to the Underground companies under this Part of this Schedule there shall not be taken into account any increase in the sums claimed that is attributable to any action taken by or any agreement entered into by the Underground companies if that action or agreement was not reasonably necessary and was taken or entered into with a view to obtaining the payment of those sums by DLRL under this Part of this Schedule or increasing the sums so payable.
Notes on Schedule 11
Modifications
- C1
Sch. 11 modified (31.12.2020) by The Railway (Licensing of Railway Undertakings) (Amendment etc.) (EU Exit) Regulations 2019 (S.I. 2019/700), regs. 1(2), 41; 2020 c. 1, Sch. 5 para. 1(1)