DLRL shall repay to Railtrack PLC all reasonable fees, costs, charges and expenses reasonably incurred by Railtrack—

(a)

in constructing any part of a specified work on behalf of DLRL as provided by paragraph 3(3) above or in constructing any protective works under the provisions of paragraph 3(5) above including, in respect of any permanent protective works, a capitalised sum representing the cost of maintaining and renewing those works; and

(b)

in respect of the approval by the engineer of plans submitted by DLRL and the supervision by him of the construction of a specified work.

Notes on Schedule 11

Modifications

C1

Sch. 11 modified (31.12.2020) by The Railway (Licensing of Railway Undertakings) (Amendment etc.) (EU Exit) Regulations 2019 (S.I. 2019/700), regs. 1(2), 41; 2020 c. 1, Sch. 5 para. 1(1)