OpenLegislation

Introductory text

Original text. Later amendments are not shown.

Infrastructure Planning

Made 2nd October 2015

Coming into force 5th October 2015

The Dogger Bank Creyke Beck Offshore Wind Farm Order 2015 (the “Order”)f1, which granted development consent within the meaning of the Planning Act 2008 (the “Act”)f2, contained correctable errors within the meaning of the Act.

In accordance with paragraph 1(5)(a) of Schedule 4 to the Act, the Secretary of State received, before the end of the relevant period referred to in paragraph 1(6)(a) of that Schedule, a written request from Forewind Limited to correct errors and omissions in the Order. In accordance with paragraph 1(7) of that Schedule, the Secretary of State informed the East Riding of Yorkshire Council that the request had been received.

The Secretary of State, in exercise of the powers in paragraph 1(4) and (8) of that Schedule, makes the following Order:

Annotations

Footnotes

f1

S.I. 2015/318.

f2

2008 c.29. Paragraph 1 of Schedule 4 was amended by paragraph 70 of Schedule 13, and Part 20 of Schedule 25, to the Localism Act 2011 (c.20) and by paragraph 4 of Schedule 8 to the Marine and Coastal Access Act 2009 (c.23). There are other amendments to the Act which are not relevant to this Order.