The Dogger Bank Creyke Beck Offshore Wind Farm Order 2015
S.I. 2015/318 · Made 17 February 2015 · Extends to England, Wales and Scotland
Infrastructure Planning
Made 17th February 2015
Coming into force 11th March 2015
An application under section 37 of the Planning Act 2008f1 (the “2008 Act”) has been made to the Secretary of State for an order granting development consent.
The application has been examined by a Panel, which has made a report to the Secretary of State under section 74(2) of the 2008 Act.
The Secretary of State has considered the report and recommendation of the Panel, has taken into account the environmental information in accordance with regulation 3 of the Infrastructure Planning (Environmental Impact Assessment) Regulations 2009f2 and has had regard to the documents and matters referred to in section 104(2) of the 2008 Act.
The Secretary of State is satisfied that the special category land (as defined in article 34 of the Order), when burdened with the order rights (as defined in that article), will be no less advantageous that it was before to the persons in whom it is vested; other persons, if any, entitled to rights of common or other rights; and the public and that, accordingly, section 132(3) of the 2008 Act applies.
The Secretary of State, having decided the application, has determined to make an order giving effect to the proposals comprised in the application with modifications that in the opinion of the Secretary of State do not make any substantial change to the proposals.
Accordingly, the Secretary of State, in exercise of the powers in sections 114 and 120 of the 2008 Act, makes the following Order:
Annotations to the whole text
Footnotes
- f1
-
2008 c.29. Section 37 was amended by section 137(5) of, and paragraph 5 of Schedule 13 to, the Localism Act 2011 (c.20). Section 74(2) was amended by paragraph 29(2) of that Schedule. Section 104(2) was amended by paragraph 49 of that Schedule and section 58 of the Marine and Coastal Access Act 2009 (c.23). Section 114 was amended by paragraph 55 of Schedule 13 to the Localism Act 2011. Section 120 was amended by section 140 of, and paragraph 60 of Schedule 13 to, that Act. Section 132 was amended by section 24(3) of the Growth and Infrastructure Act 2013 (c.27).
- f2
-
S.I. 2009/2263; relevant amending instruments are S.I. 2012/635 and 2012/787.
Contents
- Part 1: Preliminary
- 1Citation and commencement
- 2Interpretation
- Part 2: Principal powers
- 3Development consent, etc. granted by Order
- 4Maintenance of authorised project
- 5Operation of generating stations
- 6Requirements: appeals, etc.
- 7Benefit of Order
- 8Consent to transfer benefit of Order
- 9Bizco 1 and Bizco 4 may enter certain land for purpose of construction
- 10Disapplication and modification of legislative provisions
- 11Offshore works: abandonment, decay or removal
- 12Defence to proceedings in respect of statutory nuisance
- Part 3: Streets
- 13Street works
- 14Temporary stopping up of streets
- 15Access to works
- 16Agreements with street authorities
- Part 4: Supplemental powers
- 17Discharge of water
- 18Protective work to buildings
- 19Authority to survey and investigate land
- 20Removal of human remains
- Part 5: Powers of acquisition
- 21Compulsory acquisition of land
- 22Compulsory acquisition of land: minerals
- 23Time limit for exercise of authority to acquire land compulsorily, etc.
- 24Compulsory acquisition of rights
- 25Private rights of way
- 26Application of Compulsory Purchase (Vesting Declarations) Act 1981
- 27Acquisition of part of certain properties
- 28Rights under or over streets
- 29Temporary use of land for carrying out authorised project
- 30Temporary use of land for maintaining authorised project
- 31Statutory undertakers
- 32Recovery of costs of new connections
- 33Application of landlord and tenant law
- 34Special category land
- Part 6: Miscellaneous and general
- 35Railway and navigation undertakings
- 36Trees subject to tree preservation orders
- 37Operational land for purposes of 1990 Act
- 38Felling or lopping of trees and removal of hedgerows
- 39Deemed licences under Marine and Coastal Access Act 2009
- 40Saving for Trinity House
- 41Crown rights
- 42Certification of plans and documents, etc.
- 43Protective provisions
- 44Arbitration
- Signature
- Schedule 1: Authorised project
- 1Authorised development
- 2Ancillary works
- Part 3: Requirements
- 1Interpretation
- 2Time limits
- 3Detailed offshore design parameters
- 4Detailed offshore design parameters
- 5Detailed offshore design parameters
- 6Detailed offshore design parameters
- 7Layout rules
- 8Aviation lighting
- 9Aviation lighting
- 10Offshore decommissioning
- 11Stages of authorised development onshore
- 12Detailed design approval onshore
- 13Detailed design approval onshore
- 14Provision of landscaping
- 15Implementation and maintenance of landscaping
- 16Fencing and other means of enclosure
- 17Highway accesses
- 18Surface and foul water drainage
- 19Surface and foul water drainage
- 20Archaeology
- 21Ecological management plan
- 22Code of construction practice, etc.
- 23Construction environmental management plan
- 24Construction hours
- 25Control of noise during operational phase
- 26Control of artificial light emissions
- 27Construction-phase traffic management plan
- 28European protected species: onshore
- 29Restoration of land used temporarily for construction
- 30Interference with telecommunications
- 31Onshore decommissioning
- 32Emergency response plan
- 33Amendments to approved details
- 34Southern North Sea Special Area of Conservation
- Schedule 2Streets subject to street works
- Schedule 3Streets to be temporarily stopped up
- Schedule 4Access to works
- Schedule 5Land over which only new rights may be acquired
- Schedule 6: Modification of compensation and compulsory purchase enactments for creation of new rights
- 1Compensation enactments modified
- 2Land Compensation Act 1973 modified
- 3Compulsory Purchase Act 1965 modified
- Schedule 7Land of which temporary possession may be taken
- Schedule 8: Marine Licence 1: Project A Offshore (Generation – Works No. 1A and 2T)
- Part A: Licensed activities
- 1Interpretation
- 2Details of licensed activities
- Part B: Conditions
- 3Detailed offshore design parameters
- 4Detailed offshore design parameters
- 5Layout rules
- 6Notifications and inspections
- 7Chemicals, drilling and debris
- 8Force majeure
- 9Pre-construction plans and documentation
- 10Pre-construction plans and documentation
- 11Offshore safety management
- 12Reporting of engaged agents, contractors and vessels
- 13Equipment and operation of vessels engaged in licensed activities
- 14Pre-construction monitoring
- 15Construction monitoring
- 16Post-construction surveys
- 17Post-construction maintenance plan
- 18Aids to navigation
- 19Aids to navigation
- 20Aids to navigation
- 21Aids to navigation
- 22Aids to navigation
- 23Aids to navigation
- 24Colour of authorised scheme
- 25Amendments to plans, etc.
- Schedule 9: Marine Licence 2: Project B Offshore (Generation – Works No. 1B and 2T)
- Part A: Licensed activities
- 1Interpretation
- 2Details of licensed activities
- Part B: Conditions
- 3Detailed offshore design parameters
- 4Detailed offshore design parameters
- 5Layout rules
- 6Notifications and inspections
- 7Chemicals, drilling and debris
- 8Force majeure
- 9Pre-construction plans and documentation
- 10Pre-construction plans and documentation
- 11Offshore safety management
- 12Reporting of engaged agents, contractors and vessels
- 13Equipment and operation of vessels engaged in licensed activities
- 14Pre-construction monitoring
- 15Construction monitoring
- 16Post-construction surveys
- 17Post-construction maintenance plan
- 18Aids to navigation
- 19Aids to navigation
- 20Aids to navigation
- 21Aids to navigation
- 22Aids to navigation
- 23Aids to navigation
- 24Colour of authorised scheme
- 25Amendments to plans, etc.
- Schedule 10: Marine Licence 3: Project A Offshore (Transmission – Works No. 2A, 3A and 2T)
- Part A: Licensed activities
- 1Interpretation
- 2Details of licensed activities
- Part B: Conditions
- 3Detailed offshore design parameters
- 4Layout rules
- 5Notifications and inspections
- 6Chemicals, drilling and debris
- 7Force majeure
- 8Pre-construction plans and documentation
- 9Pre-construction plans and documentation
- 10Offshore safety management
- 11Reporting of engaged agents, contractors and vessels
- 12Equipment and operation of vessels engaged in licensed activities
- 13Pre-construction monitoring
- 14Construction monitoring
- 15Post-construction surveys
- 16Post-construction maintenance plan
- 17Aids to navigation
- 18Aids to navigation
- 19Aids to navigation
- 20Aids to navigation
- 21Aids to navigation
- 22Aids to navigation
- 23Colour of authorised scheme
- 24Amendments to plans, etc.
- Schedule 11: Marine Licence 4: Project B Offshore (Transmission Works No. 2B, 2BA or 2BC, 3B and 2T)
- Part A: Licensed activities
- 1Interpretation
- 2Details of licensed activities
- Part B: Conditions
- 3Detailed offshore design parameters
- 4Layout rules
- 5Notifications and inspections
- 6Chemicals, drilling and debris
- 7Force majeure
- 8Pre-construction plans and documentation
- 9Pre-construction plans and documentation
- 10Offshore safety management
- 11Reporting of engaged agents, contractors and vessels
- 12Equipment and operation of vessels engaged in licensed activities
- 13Pre-construction monitoring
- 14Construction monitoring
- 15Post-construction surveys
- 16Post-construction maintenance plan
- 17Aids to navigation
- 18Aids to navigation
- 19Aids to navigation
- 20Aids to navigation
- 21Aids to navigation
- 22Aids to navigation
- 23Colour of authorised scheme
- 24Amendments to plans, etc.
- Schedule 12: Protective provisions
- Part 1: Protection of electricity, gas, water and sewerage undertakers
- 1Paragraph 1
- 2Paragraph 2
- 3Paragraph 3
- 4Paragraph 4
- 5Paragraph 5
- 6Paragraph 6
- 7Paragraph 7
- 8Paragraph 8
- 9Paragraph 9
- 10Paragraph 10
- 11Paragraph 11
- Part 2: Protection of Network Rail Infrastructure Limited
- 1Paragraph 1
- 2Paragraph 2
- 3Paragraph 3
- 4Paragraph 4
- 5Paragraph 5
- 6Paragraph 6
- 7Paragraph 7
- 8Paragraph 8
- 9Paragraph 9
- 10Paragraph 10
- 11Paragraph 11
- 12Paragraph 12
- 13Paragraph 13
- 14Paragraph 14
- 15Paragraph 15
- 16Paragraph 16
- 17Paragraph 17
- 18Paragraph 18
- 19Paragraph 19
- 20Paragraph 20
- 21Paragraph 21
- Part 3: Protection of operators of electronic communications code networks
- 1Paragraph 1
- 2Paragraph 2
- 3Paragraph 3
- Part 4: Protection of offshore cables and pipelines
- 1Paragraph 1
- 2Paragraph 2
- 3Paragraph 3
- 4Paragraph 4
- 5Paragraph 5
- 6Paragraph 6
- 7Paragraph 7
- 8Paragraph 8
- 9Paragraph 9
- 10Paragraph 10
- 11Paragraph 11
- 12Paragraph 12
- 13Paragraph 13
- 14Paragraph 14
- 15Paragraph 15
- 16Paragraph 16
- Part 5: Protection of Environment Agency
- 1Paragraph 1
- 2Paragraph 2
- 3Paragraph 3
- 4Paragraph 4
- 5Paragraph 5
- 6Paragraph 6
- 7Paragraph 7
- 8Paragraph 8
- 9Paragraph 9
- 10Paragraph 10
- 11Paragraph 11
- 12Paragraph 12
- Explanatory note