Paragraph 5 I1

England, Wales and Scotland

The undertaker must use its best endeavours—

(a)

in exercising any of the powers in this Order to avoid or (failing avoidance) to minimise any damage or disruption to the protected property; and

(b)

without limiting sub-paragraph (a), to ensure that the works do not at any time fall into such a condition as to compromise the integrity or operation of the protected property.

Annotations

Commencement

I1

Sch. 12 Pt. 4 para. 5 in force at 11.3.2015, see art. 1

Notes on Schedule 12

Modifications

C1

Sch. 12 modified (3.8.2023) by The Hornsea Four Offshore Wind Farm Order 2023 (S.I. 2023/800), arts. 1, 46, Sch. 13 (with arts. 42, 43, Sch. 9 Pt. 1 para. 4, Sch. 9 Pt. 3 para. 6(1), Sch. 9 Pt. 4 para. 20, Sch. 9 Pt. 9 para. 4) (as amended (31.1.2024) by The Hornsea Four Offshore Wind Farm (Correction) Order 2024 (S.I. 2024/117), Sch.)