Paragraph 6 I1
England, Wales and Scotland
Not less than 8 months before commencing construction of the works, the undertaker must furnish to the Company a programme for the works proposed and a general indication of the nature and location of those works and, if within 28 days from the receipt by a Company of that programme and general indication the Company gives notice in writing to the undertaker that any part of the offshore works indicated in the programme may in any way affect protected property, paragraphs 8 and 9 apply with respect to that part of those works.
Annotations
Commencement
- I1
Sch. 12 Pt. 4 para. 6 in force at 11.3.2015, see art. 1
Notes on Schedule 12
Modifications
- C1
Sch. 12 modified (3.8.2023) by The Hornsea Four Offshore Wind Farm Order 2023 (S.I. 2023/800), arts. 1, 46, Sch. 13 (with arts. 42, 43, Sch. 9 Pt. 1 para. 4, Sch. 9 Pt. 3 para. 6(1), Sch. 9 Pt. 4 para. 20, Sch. 9 Pt. 9 para. 4) (as amended (31.1.2024) by The Hornsea Four Offshore Wind Farm (Correction) Order 2024 (S.I. 2024/117), Sch.)