Paragraph 21 Ecological management planI1

England, Wales and Scotland

(1)

No stage of the onshore works must commence until a written ecological management plan for the onshore works reflecting the survey results and ecological mitigation and enhancement measures included in the environmental statement for that stage has been submitted to and approved in writing by the relevant planning authority following consultation with the relevant statutory nature conservation body.

(2)

The ecological management plan must include an implementation timetable and must be carried out as approved by the relevant planning authority.