Paragraph 9 Pre-construction plans and documentationI1
England, Wales and Scotland
(1)
Each programme, statement, plan, protocol, scheme or details required to be approved under Condition 8, and the arrangements required to be approved under Condition 4, must be submitted for approval at least 4 months before the intended commencement of construction, except where otherwise stated or unless otherwise agreed in writing by the MMO.
(2)
The licensed activities must be carried out in accordance with the programme, statement, plan, protocol, scheme or details approved under Condition 8.
Annotations
Commencement
- I1
Sch. 11 para. 9 in force at 11.3.2015, see art. 1