Paragraph 19 Surface and foul water drainageI1
England, Wales and Scotland
F1The Project A converter station works must not commence until a detailed scheme addressing the matters referred to in sub-paragraph (2) has been submitted to and approved in writing by the relevant planning authority following consultation with the Environment Agency.
The Project B converter station works must not commence until a detailed scheme addressing the matters referred to in sub-paragraph (2) has been submitted to and approved in writing by the relevant planning authority following consultation with the Environment Agency.
F3Each scheme must take account of the mitigation measures in relation to operational activities at the converter station site, as detailed within section 7 of Chapter 24 of the environmental statement, and must include—
details of any proposed underground oil separators, including the full structural details of the installation and the mitigation to be embedded into the design of the installation in order to protect ground and surface waters;
details of the proposed storage bund installations, including full structural details of the installation and the mitigation to be embedded into the design of the installation in order to protect ground and surface waters; and
an emergency plan, including provisions to ensure that controlled waters are protected in an emergency event.
F4Each scheme must be implemented as approved in writing by the relevant planning authority.
Annotations
Textual amendments
- F1
Words in Sch. 1 para. 19(1) substituted (21.11.2025) by The Dogger Bank Creyke Beck Offshore Wind Farm (Amendment) Order 2025 (S.I. 2025/1264), arts. 1, 8(a)
- F2
Sch. 1 para. 19(1A) inserted (21.11.2025) by The Dogger Bank Creyke Beck Offshore Wind Farm (Amendment) Order 2025 (S.I. 2025/1264), arts. 1, 8(b)
- F3
Words in Sch. 1 para. 19(2) substituted (21.11.2025) by The Dogger Bank Creyke Beck Offshore Wind Farm (Amendment) Order 2025 (S.I. 2025/1264), arts. 1, 8(c)
- F4
Words in Sch. 1 para. 19(3) substituted (21.11.2025) by The Dogger Bank Creyke Beck Offshore Wind Farm (Amendment) Order 2025 (S.I. 2025/1264), arts. 1, 8(c)