Paragraph 8 I1
England, Wales and Scotland
Not less than 4 months before commencing construction of any part of the offshore works that may significantly affect the protected property, the undertaker must furnish to the Company detailed plans and specifications of the relevant part of the offshore works and must have due regard to any representations made by a Company relating to such plans or to the programme for the works and make reasonable changes required to avoid risk of harm to the cables by the construction.
Annotations
Commencement
- I1
Sch. 12 Pt. 4 para. 8 in force at 11.3.2015, see art. 1
Notes on Schedule 12
Modifications
- C1
Sch. 12 modified (3.8.2023) by The Hornsea Four Offshore Wind Farm Order 2023 (S.I. 2023/800), arts. 1, 46, Sch. 13 (with arts. 42, 43, Sch. 9 Pt. 1 para. 4, Sch. 9 Pt. 3 para. 6(1), Sch. 9 Pt. 4 para. 20, Sch. 9 Pt. 9 para. 4) (as amended (31.1.2024) by The Hornsea Four Offshore Wind Farm (Correction) Order 2024 (S.I. 2024/117), Sch.)