Paragraph 23 Colour of authorised schemeI1
England, Wales and Scotland
(1)
The undertaker must colour all structures that are part of the authorised scheme seaward of MHWS yellow (colour code RAL 1023) from at least HAT to a height approved by the MMO following consultation with Trinity House.
(2)
Details of the remainder of the structures must be submitted to and approved in writing by the MMO following consultation with Trinity House before commencement of the authorised scheme.
(3)
The structures must be coloured in accordance with the approved details.
Annotations
Commencement
- I1
Sch. 11 para. 23 in force at 11.3.2015, see art. 1