Paragraph 13 Phases of authorised scheme
(1)
The authorised scheme must not commence until an offshore works phasing scheme setting out the phases of construction of the authorised scheme has been submitted to and approved in writing by the MMO.
(2)
The authorised scheme must be submitted at least 6 months prior to the proposed commencement of the works.
(3)
Any subsequent amendments to the offshore works phasing scheme submitted for approval under sub-paragraph (1) must be submitted to the MMO for approval in writing.
(4)
The offshore works phasing scheme submitted for approval under sub-paragraph (1) must be implemented as approved. The approved details shall be taken to include any amendment that may subsequently be approved by the MMO in accordance with sub-paragraph (3).