OpenLegislation

The Dogger Bank South East and West Offshore Wind Farms Order 2026

S.I. 2026/577 · Made 14 May 2026

Original text. legislation.gov.uk does not revise statutory instruments, so later amendments are not shown here. Changes made to it are listed under each provision when known.

Infrastructure Planning

Made 14th May 2026

Coming into force 5th June 2026

An application has been made to the Secretary of State under section 37 of the Planning Act 2008f1 (the “2008 Act”) and in accordance with the Infrastructure Planning (Applications: Prescribed Forms and Procedures) Regulations 2009f2 for an order granting development consent.

The application was examined by the Examining Authority appointed by the Secretary of State pursuant to section 61f3 and 65f4 of Part 6 of the 2008 Act, and the examination was carried out in accordance with Chapter 4 of that Act and with the Infrastructure Planning (Examination Procedure) Rules 2010f5. The Examining Authority has made a report and recommendation to the Secretary of State under section 74(2)f6 of the 2008 Act.

The Secretary of State has considered representations made and not withdrawn and the report and recommendation of the Examining Authority, has taken into account the environmental information in accordance with regulation 4 of the Infrastructure Planning (Environmental Impact Assessment) Regulations 2017f7 and, as a national policy statement has effect in relation to the proposed development, has had regard to the documents and matters referred to in section 104(2)f8 of the 2008 Act.

The Secretary of State is satisfied that open space land within the Order land, when burdened with the new rights or the imposition of a restrictive covenant as authorised for compulsory acquisition under the terms of this Order, will be no less advantageous than it was before such acquisition to the persons in whom it is vested, other persons, if any, entitled to rights of common or other rights, and the public, and that, accordingly, section 132(3)f9 of the 2008 Act applies.

The Secretary of State, having decided the application, has determined to make an order granting development consent for the development described in the application with modifications which in the opinion of the Secretary of State do not make any substantial changes to the proposals comprised in the application.

Accordingly, the Secretary of State, in exercise of the powers in sections 114, 115, 120f10, 122, 123, 132, 140 and 149A of the 2008 Act, makes the following Order.

Annotations to the whole text

Footnotes

f1

2008 c. 29. Section 37 was amended by Chapter 6 of Part 6 of, and Schedule 13 to, the Localism Act 2011 (c. 20).

f2

S.I. 2009/2264.

f3

Section 61 was amended by section 128(2) of, and paragraph 18 Schedule 13, to the Localism Act 2011 (c. 20) and by section 26 of the Infrastructure Act 2015 (c. 7).

f4

Section 65 was amended by paragraph 22(2) of Schedule 13 and paragraph 1 of Schedule 25 to the Localism Act 2011 (c. 20) and by section 27(1) of the Infrastructure Act 2015 (c. 7).

f5

S.I. 2010/2013, amended by S.I. 2012/635.

f6

Section 74 was amended by sections 128(2) and 237 of, and by paragraph 29 of Schedule 13 and paragraph 1 of Schedule 25, to the Localism Act 2011.

f7

S.I. 2017/572.

f8

Section 104 was amended by section 58(5) of the Marine and Coastal Access Act 2009 (c. 23) and by section 128(2) of, and paragraphs 1 and 49(1) to (6) of Schedule 13 to, the Localism Act 2011.

f9

Section 132 was amended by section 24(3) of the Growth and Infrastructure Act 2013 (c. 27).

f10

Sections 114, 115 and 120 were amended by sections 128(2) and 140 of, and paragraphs 1, 55(1) and (2) and 60(1) and (3) of Schedule 13 to, the Localism Act 2011. Relevant amendments were made to section 115 by section 160(1) to (6) of the Housing and Planning Act 2016 (c. 22).

Contents

  1. Part 1: Preliminary
  2. 1Citation and commencement
  3. 2Interpretation
  4. Part 2: Principal powers
  5. 3Development consent granted by Order
  6. 4Power to maintain the authorised project
  7. 5Benefit of the Order
  8. 6Disapplication and modification of legislative provisions
  9. 7Defence to proceedings in respect of statutory nuisance
  10. Part 3: Streets
  11. 8Street works
  12. 9Application of the 1991 Act
  13. 10Temporary closure of streets
  14. 11Closure and diversion of public rights of way
  15. 12Power to alter layout, etc. of streets
  16. 13Access to works
  17. 14Agreements with street authorities
  18. 15Use of private roads
  19. Part 4: Supplemental powers
  20. 16Discharge of water
  21. 17Protective work to buildings
  22. 18Authority to survey and investigate land onshore
  23. 19Article not used
  24. Part 5: Powers of acquisition
  25. 20Compulsory acquisition of land
  26. 21Time limit for exercise of authority to acquire land compulsorily
  27. 22Compulsory acquisition of rights
  28. 23Private rights over land
  29. 24Application of the 1981 Act
  30. 25Statutory authority to override easements and other rights
  31. 26Acquisition of subsoil or airspace only
  32. 27Compulsory acquisition of land: minerals
  33. 28Modification of Part 1 of the 1965 Act
  34. 29Rights under or over streets
  35. 30Temporary use of land for carrying out the authorised project
  36. 31Temporary use of land for maintaining the authorised project
  37. 32Statutory undertakers
  38. 33Recovery of costs of new connections
  39. Part 6: Operations
  40. 34Operation of generating station
  41. 35Deemed marine licences under the 2009 Act
  42. Part 7: Miscellaneous and general
  43. 36Application of landlord and tenant law
  44. 37Operational land for purposes of the 1990 Act
  45. 38Felling or lopping of trees and removal of hedgerows
  46. 39Trees subject to tree preservation orders
  47. 40Saving provisions for Trinity House
  48. 41Crown rights
  49. 42Certification of plans and documents, etc.
  50. 43Abatement of works abandoned or decayed
  51. 44Funding
  52. 45Protective provisions
  53. 46Service of notices
  54. 47Arbitration
  55. 48Procedure in relation to certain approvals etc.
  56. 49Compensation
  57. 50No double recovery
  58. Signature
  59. Schedule 1: Authorised project
  60. 1Authorised development
  61. 1Paragraph 1
  62. Part 2: Ancillary works
  63. 2Paragraph 2
  64. Schedule 2
  65. 1Requirements
  66. 1Time limits
  67. 7Offshore decommissioning
  68. 8Phases of authorised development
  69. 9Detailed design parameters onshore
  70. 10Provision of landscaping
  71. 11Implementation and maintenance of landscaping
  72. 12Ecological management plan
  73. 13Permanent fencing and other means of enclosure
  74. 14Traffic and Transport
  75. 15Highway accesses
  76. 16Pre-commencement, Construction and Operational Drainage Strategy
  77. 17Foul Water Drainage
  78. 18Onshore Archaeology
  79. 19Code of construction practice
  80. 20Construction hours for the onshore works
  81. 21Control of noise during operational phase
  82. 22Control of artificial light emissions
  83. 23European protected species: onshore
  84. 24Public Rights of Way Management Plan
  85. 25Restoration of land used temporarily for construction
  86. 26Skills and employment
  87. 27Onshore decommissioning
  88. 28Notification of generation of power
  89. 29Contaminated land and groundwater scheme
  90. 30Port traffic
  91. 31Ministry of Defence Radar Mitigation
  92. 32Biodiversity net gain
  93. 33Onshore monitoring plan
  94. 34Amendments to approved details
  95. 35Onshore collaboration
  96. 36Permanent access road to onshore converter stations
  97. 37Wake effects plan
  98. Part 2: Approval of matters specified in requirements
  99. 38Applications made under requirements
  100. 39Applications made under requirements
  101. 40Further information
  102. 41Appeal
  103. Schedule 3: Streets subject to street works
  104. 1Streets subject to permanent street works
  105. 2Streets subject to temporary street works
  106. Schedule 4Streets to be temporarily closed or restricted
  107. Schedule 5: Closure and diversion of public rights of way
  108. 1Public rights of way to be temporarily closed or restricted
  109. 2Public rights of way to be permanently diverted
  110. Schedule 6Access to works
  111. Schedule 7Land in which only new rights, etc. may be acquired
  112. Schedule 8: Modification of compensation and compulsory purchase enactments for creation of new rights and imposition of restrictive covenants
  113. 1Compensation enactments
  114. 2Compensation enactments
  115. 3Compensation enactments
  116. 4Application of Part 1 of the 1965 Act
  117. 5Application of Part 1 of the 1965 Act
  118. Schedule 9Land of which only temporary possession may be taken
  119. Schedule 10: Deemed Marine Licence 1: DBS East Project Offshore Generation – Work Nos. 1A, 4A and 7A
  120. Part 1: Licensed marine activities
  121. 1Interpretation
  122. 2Details of licensed marine activities
  123. 3Details of licensed marine activities
  124. 4Details of licensed marine activities
  125. 5Details of licensed marine activities
  126. 6Details of licensed marine activities
  127. 7Details of licensed marine activities
  128. 8Details of licensed marine activities
  129. 9Details of licensed marine activities
  130. 2Conditions
  131. 15Phases of authorised scheme
  132. 16Maintenance of the authorised scheme
  133. 17Extension of time periods
  134. 18Notifications and inspections
  135. 19Aids to navigation
  136. 20Colouring of Structures
  137. 21Aviation safety
  138. 22Chemicals, drilling and debris
  139. 23Force majeure
  140. 24Pre-construction plans and documentation
  141. 25Site Integrity Plan
  142. 26Approval of programmes, statements etc.
  143. 27Offshore safety management
  144. 28Reporting of engaged agents, contractors and vessels
  145. 29Pre-construction monitoring and surveys
  146. 30Construction monitoring and surveys
  147. 31Post-construction monitoring and surveys
  148. 32Reporting of scour and cable protection
  149. 33Completion of construction
  150. 34Collaboration
  151. 35Reporting of impact pile driving
  152. 36Maintenance reporting
  153. 37Sediment Sampling
  154. 38Ornithological monitoring
  155. 39Noise restriction
  156. Schedule 11: Deemed Marine Licence 2: DBS West Project Offshore Generation – Work Nos. 1B, 4B and 7B
  157. Part 1: Licensed marine activities
  158. 1Interpretation
  159. 2Details of licensed marine activities
  160. 3Details of licensed marine activities
  161. 4Details of licensed marine activities
  162. 5Details of licensed marine activities
  163. 6Details of licensed marine activities
  164. 7Details of licensed marine activities
  165. 8Details of licensed marine activities
  166. 9Details of licensed marine activities
  167. 2Conditions
  168. 15Phases of authorised scheme
  169. 16Maintenance of the authorised scheme
  170. 17Extension of time periods
  171. 18Notifications and inspections
  172. 19Aids to navigation
  173. 20Colouring of Structures
  174. 21Aviation safety
  175. 22Chemicals, drilling and debris
  176. 23Force majeure
  177. 24Pre-construction plans and documentation
  178. 25Site Integrity Plan
  179. 26Approval of programmes, statements etc.
  180. 27Offshore safety management
  181. 28Reporting of engaged agents, contractors and vessels
  182. 29Pre-construction monitoring and surveys
  183. 30Construction monitoring and surveys
  184. 31Post-construction monitoring and surveys
  185. 32Reporting of scour and cable protection
  186. 33Completion of construction
  187. 34Collaboration
  188. 35Reporting of impact pile driving
  189. 36Maintenance reporting
  190. 37Sediment Sampling
  191. 38Ornithological monitoring
  192. 39Noise restriction
  193. Schedule 12: Deemed Marine Licence 3: DBS East Project Offshore Transmission – Work Nos. 2A, 3A, 7A and 8A
  194. Part 1: Licensed marine activities
  195. 1Interpretation
  196. 2Details of licensed marine activities
  197. 3Details of licensed marine activities
  198. 4Details of licensed marine activities
  199. 5Details of licensed marine activities
  200. 6Details of licensed marine activities
  201. 7Details of licensed marine activities
  202. 8Details of licensed marine activities
  203. 9Details of licensed marine activities
  204. 2Conditions
  205. 13Phases of authorised scheme
  206. 14Maintenance of the authorised scheme
  207. 15Extension of time periods
  208. 16Notifications and inspections
  209. 17Aids to navigation
  210. 18Colouring of Structures
  211. 19Aviation safety
  212. 20Chemicals, drilling and debris
  213. 21Force majeure
  214. 22Pre-construction plans and documentation
  215. 23Site Integrity Plan
  216. 24Approval of programmes, statements etc.
  217. 25Offshore safety management
  218. 26Reporting of engaged agents, contractors and vessels
  219. 27Pre-construction monitoring and surveys
  220. 28Construction monitoring and surveys
  221. 29Post-construction monitoring and surveys
  222. 30Reporting of scour and cable protection
  223. 31Completion of construction
  224. 32Collaboration
  225. 33Reporting of impact pile driving
  226. 34Maintenance reporting
  227. 35Sediment Sampling
  228. 36Noise restriction
  229. 37Export cable restriction
  230. Schedule 13: Deemed Marine Licence 4: DBS West Project Offshore Transmission – Work Nos. 2B, 3B, 7B and 8B
  231. Part 1: Licensed marine activities
  232. 1Interpretation
  233. 2Details of licensed marine activities
  234. 3Details of licensed marine activities
  235. 4Details of licensed marine activities
  236. 5Details of licensed marine activities
  237. 6Details of licensed marine activities
  238. 7Details of licensed marine activities
  239. 8Details of licensed marine activities
  240. 9Details of licensed marine activities
  241. 2Conditions
  242. 13Phases of authorised scheme
  243. 14Maintenance of the authorised scheme
  244. 15Extension of time periods
  245. 16Notifications and inspections
  246. 17Aids to navigation
  247. 18Colouring of Structures
  248. 19Aviation safety
  249. 20Chemicals, drilling and debris
  250. 21Force majeure
  251. 22Pre-construction plans and documentation
  252. 23Site Integrity Plan
  253. 24Approval of programmes, statements etc.
  254. 25Offshore safety management
  255. 26Reporting of engaged agents, contractors and vessels
  256. 27Pre-construction monitoring and surveys
  257. 28Construction monitoring and surveys
  258. 29Post-construction monitoring and surveys
  259. 30Reporting of scour and cable protection
  260. 31Completion of construction
  261. 32Collaboration
  262. 33Reporting of impact pile driving
  263. 34Maintenance reporting
  264. 35Sediment Sampling
  265. 36Noise restriction
  266. 37Export cable restriction
  267. Schedule 14: Deemed Marine Licence 5: DBS East Project Offshore Transmission – Work Nos. 5A and 7A
  268. Part 1: Licensed marine activities
  269. 1Interpretation
  270. 2Details of licensed marine activities
  271. 3Details of licensed marine activities
  272. 4Details of licensed marine activities
  273. 5Details of licensed marine activities
  274. 6Details of licensed marine activities
  275. 7Details of licensed marine activities
  276. 8Details of licensed marine activities
  277. 9Details of licensed marine activities
  278. 2Conditions
  279. 11Phases of authorised scheme
  280. 12Maintenance of the authorised scheme
  281. 13Extension of time periods
  282. 14Notifications and inspections
  283. 15Aids to navigation
  284. 16Not used
  285. 17Aviation safety
  286. 18Chemicals, drilling and debris
  287. 19Force majeure
  288. 20Pre-construction plans and documentation
  289. 21Offshore safety management
  290. 22Reporting of engaged agents, contractors and vessels
  291. 23Pre-construction monitoring and surveys
  292. 24Construction monitoring and surveys
  293. 25Post-construction monitoring and surveys
  294. 26Reporting of scour and cable protection
  295. 27Completion of construction
  296. 28Collaboration
  297. 29Maintenance reporting
  298. 30Sediment Sampling
  299. 31Notification of works
  300. Schedule 14A: Deemed Marine Licence 6: DBS West Project Offshore Transmission – Work Nos. 5B and 7B
  301. Part 1: Licensed marine activities
  302. 1Interpretation
  303. 2Details of licensed marine activities
  304. 3Details of licensed marine activities
  305. 4Details of licensed marine activities
  306. 5Details of licensed marine activities
  307. 6Details of licensed marine activities
  308. 7Details of licensed marine activities
  309. 8Details of licensed marine activities
  310. 9Details of licensed marine activities
  311. 2Conditions
  312. 11Phases of authorised scheme
  313. 12Maintenance of the authorised scheme
  314. 13Extension of time periods
  315. 14Notifications and inspections
  316. 15Aids to navigation
  317. 16Not used
  318. 17Aviation safety
  319. 18Chemicals, drilling and debris
  320. 19Force majeure
  321. 20Pre-construction plans and documentation
  322. 21Offshore safety management
  323. 22Reporting of engaged agents, contractors and vessels
  324. 23Pre-construction monitoring and surveys
  325. 24Construction monitoring and surveys
  326. 25Post-construction monitoring and surveys
  327. 26Reporting of scour and cable protection
  328. 27Completion of construction
  329. 28Collaboration
  330. 29Maintenance reporting
  331. 30Sediment Sampling
  332. 31Notification of works
  333. Schedule 15: Protective provisions
  334. Part 1: Protection of electricity, gas, water and sewerage undertakers
  335. 1Application
  336. 2Interpretation
  337. 3On street apparatus and offshore works
  338. 4Acquisition of land
  339. 5Removal of apparatus
  340. 6Facilities and rights for alternative apparatus
  341. 7Retained apparatus
  342. 8Expenses and costs
  343. 9Expenses and costs
  344. 10Miscellaneous
  345. Part 2: Protection for operators of electronic communications code networks
  346. 11Paragraph 11
  347. 12Paragraph 12
  348. 13Paragraph 13
  349. 14Paragraph 14
  350. 15Paragraph 15
  351. Part 3: For the protection of the Environment Agency
  352. 16Paragraph 16
  353. 17Submission and approval of plans
  354. 18Construction of protective works
  355. 19Timing of works and service of notices
  356. 20Works not in accordance with this Schedule
  357. 21Maintenance of works
  358. 22Remediating impaired drainage work
  359. 23Agency access
  360. 24Free passage of fish
  361. 25Indemnity
  362. 26Indemnity
  363. 27Dispute
  364. Part 4: For the protection of the drainage authorities
  365. 28Paragraph 28
  366. 29Paragraph 29
  367. 30Paragraph 30
  368. 31Paragraph 31
  369. 32Paragraph 32
  370. 33Paragraph 33
  371. 34Paragraph 34
  372. 35Paragraph 35
  373. 36Paragraph 36
  374. 37Paragraph 37
  375. 38Paragraph 38
  376. 39Paragraph 39
  377. Part 5: For the protection of Network Rail Infrastructure Limited
  378. 40Paragraph 40
  379. 41Paragraph 41
  380. 42Paragraph 42
  381. 43Paragraph 43
  382. 44Paragraph 44
  383. 45Paragraph 45
  384. 46Paragraph 46
  385. 47Paragraph 47
  386. 48Paragraph 48
  387. 49Paragraph 49
  388. 50Paragraph 50
  389. 51Paragraph 51
  390. 52Paragraph 52
  391. 53Paragraph 53
  392. 54Paragraph 54
  393. 55Paragraph 55
  394. 56Paragraph 56
  395. 57Paragraph 57
  396. 58Paragraph 58
  397. 59Paragraph 59
  398. 60Paragraph 60
  399. 61Paragraph 61
  400. Part 6: For the protection of National Gas Transmission PLC as gas undertaker
  401. 62Application
  402. 63Interpretation
  403. 64On Street Apparatus
  404. 65Apparatus of National Gas in streets subject to temporary closure
  405. 66Protective works to buildings
  406. 67Acquisition of land
  407. 68Removal of apparatus
  408. 69Facilities and rights for alternative apparatus
  409. 70Retained apparatus: protection of gas undertaker
  410. 71Expenses
  411. 72Indemnity
  412. 73Enactments and agreements
  413. 74Co-operation
  414. 75Access
  415. 76Arbitration
  416. 77Notices
  417. Part 7: For the protection of National Grid Electricity Transmission PLC as electricity undertaker
  418. 78Application
  419. 79Interpretation
  420. 80Interaction with the North Humber to High Marnham Project, Wanlass Beck Project and/or the Birkhill Wood Project
  421. 81Shared area works
  422. 82Shared area works
  423. 83Shared area works
  424. 84Shared area works
  425. 85On Street Apparatus
  426. 86Apparatus of National Grid Electricity Transmission Plc in streets subject to temporary closure
  427. 87Protective works to buildings
  428. 88Acquisition of land
  429. 89Removal of apparatus
  430. 90Facilities and rights for alternative apparatus
  431. 91Retained apparatus: protection of National Grid Electricity Transmission Plc as Electricity Undertaker
  432. 92Expenses
  433. 93Indemnity
  434. 94Enactments and agreements
  435. 95Co-operation
  436. 96Access
  437. 97Arbitration
  438. 98Notices
  439. Schedule 16: Arbitration Rules
  440. 1Primary objective
  441. 2Time periods
  442. 3Timetable
  443. 4Procedure
  444. 5Arbitrator’s powers
  445. 6Costs
  446. 7Confidentiality
  447. Schedule 17: Hedgerows
  448. 1Removal of Hedgerows
  449. 2Removal of important hedgerows
  450. Schedule 18: Compensation Measures
  451. Part 1: Dogger Bank Special Area of Conservation: Delivery of measures to compensate for sandbank loss
  452. 1Paragraph 1
  453. 2Paragraph 2
  454. 3Paragraph 3
  455. Part 2: Flamborough and Filey Coast Special Protection Area: Kittiwake Compensation Measures
  456. 4Paragraph 4
  457. 5Paragraph 5
  458. 6Marine Recovery Fund
  459. 7Kittiwake CIMP
  460. 8Kittiwake CIMP
  461. 9Kittiwake CIMP
  462. 10Kittiwake CIMP
  463. 11Kittiwake CIMP
  464. 12Kittiwake CIMP
  465. 13Kittiwake CIMP
  466. 14Kittiwake CIMP
  467. 15Kittiwake CIMP
  468. 16Kittiwake CIMP
  469. Part 3: Flamborough and Filey Coast Special Protection Area and Farne Islands Special Protection Area: Guillemot Compensation Measures
  470. 17Paragraph 17
  471. 18Paragraph 18
  472. 19Marine Recovery Fund
  473. 20Guillemot CIMP
  474. 21Guillemot CIMP
  475. 22Guillemot CIMP
  476. 23Guillemot CIMP
  477. 24Guillemot CIMP
  478. 25Guillemot CIMP
  479. 26Guillemot CIMP
  480. 27Guillemot CIMP
  481. 28Guillemot CIMP
  482. Schedule 19Documents to be certified
  483. 1Documents forming the environmental statement to be certified
  484. 2Other documents to be certified
  485. Explanatory note