Paragraph 31 Completion of construction

Original text. Later amendments are not shown.

(1)

The undertaker must submit a close out report to the MMO, the MCA, Trinity House, UKHO and the relevant statutory nature conservation body within three months of the date of completion of construction. The close out report must confirm the date of completion of construction and must include the following details—

(a)

as built plans; latitude and longitude co-ordinates of the centre point of the location for each offshore converter platform, provided as Geographical Information System data referenced to WGS84 datum; and latitude and longitude co-ordinates of the export cables, provided as Geographical Information System data referenced to WGS84 datum.

(2)

Following completion of construction, no further construction activities can be undertaken under this licence.