Article 21 Time limit for exercise of authority to acquire land compulsorily
After the end of the period of seven years beginning on the day on which this Order is made—
no notice to treat is to be served under Part 1 of the 1965 Act; and
no declaration is to be executed under section 4f1 (execution of declaration) of the 1981 Act as applied by article 24 (application of the 1981 Act).
The applicable period of the purposes of section 4 of the 1965 Act (time limit for giving notice to treat) and section 5A of the 1981 Act (time limit for general vesting declaration) (as modified by this Order) is the period of seven years beginning on the day on which this Order is made.
The authority conferred by article 30 (temporary use of land for carrying out the authorised project) must not be used after the end of the applicable period referred to in paragraph (2), save that if an application is made under section 118 of the 2008 Act (legal challenges relating to applications for orders granting development consent) the applicable period is to be extended by—
a period equivalent to the period beginning on the day the application is made and ending on the day it is withdrawn or finally determined; or
if shorter, one year.
Annotations
Footnotes
- f1
-
Amended by sections 184 and 185 of, and paragraph 2 of Schedule 18 to, the Housing and Planning Act 2016 (c. 22).