Article 20 Compulsory acquisition of land
DBSEL, with the consent of DBSWL such consent not to be unreasonably withheld, may acquire compulsorily so much of the Order land as is required for the DBS East works, or to facilitate, or is incidental to, the construction, operation and maintenance of the DBS East works.
DBSWL, with the consent of DBSEL such consent not to be unreasonably withheld, may acquire compulsorily so much of the Order land as is required for the DBS West works, or to facilitate, or is incidental to, the construction, operation and maintenance of the DBS West works.
This article is subject to—
article 21 (time limit for exercise of authority to acquire land compulsorily);
paragraph (3) of article 22 (compulsory acquisition of rights);
article 26 (acquisition of subsoil or airspace only);
article 29 (rights under or over streets)
paragraph (8) of article 30 (temporary use of land for carrying out the authorised project);
article 41 (crown rights); and
Schedule 15 (protective provisions)