Where the undertaker elects to submit a Guillemot CIMP under paragraph 18(1)(b) or paragraph 18(1)(c), Work No. 1A and 1B may not commence construction until a plan for the work of the GCSG has been submitted to and approved by the Secretary of State. Such plan to include—

(a)

terms of reference of the GCSG;

(b)

details of the membership of the GCSG which must include the relevant statutory nature conservation body and, where appropriate, the MMO and/or the relevant planning authority as core members;

(c)

details of the proposed schedule of meetings, timetable for preparation of the Guillemot CIMP and reporting and review periods; and

(d)

the dispute resolution mechanism.