Cables and cable protection

10
(1)

Within Work No. 5A the inter-platform cables must not, in total—

(a)

exceed 3 in number;

(b)

exceed 138 kilometres in length;

(c)

exceed 9 cable crossings;

(d)

have cable protection (including cable crossings) exceeding 286,808 square metres in area; or

(e)

have cable protection (including cable crossings) exceeding 260,234 cubic metres in volume.

(2)

The inter-platform cables within Work No. 5A which falls within the Dogger Bank Special Area of Conservation must not have cable protection exceeding 10% of the length of such cables, when combined with the offshore export cables, array cables and inter-platform cables authorised by the licences granted under Schedules 10 to 13 and 14A of the Order.

  1. 11Phases of authorised scheme
  2. 12Maintenance of the authorised scheme
  3. 13Extension of time periods
  4. 14Notifications and inspections
  5. 15Aids to navigation
  6. 16Not used
  7. 17Aviation safety
  8. 18Chemicals, drilling and debris
  9. 19Force majeure
  10. 20Pre-construction plans and documentation
  11. 21Offshore safety management
  12. 22Reporting of engaged agents, contractors and vessels
  13. 23Pre-construction monitoring and surveys
  14. 24Construction monitoring and surveys
  15. 25Post-construction monitoring and surveys
  16. 26Reporting of scour and cable protection
  17. 27Completion of construction
  18. 28Collaboration
  19. 29Maintenance reporting
  20. 30Sediment Sampling
  21. 31Notification of works