Paragraph 24 Construction monitoring and surveys

Original text. Later amendments are not shown.

(1)

The undertaker must, in discharging condition 11(1)(b), for each phase of construction submit details (which accord with the in principle monitoring plan) for approval in writing by the MMO in consultation with the relevant statutory nature conservation bodies of any proposed monitoring and surveys, including methodologies and timings, to be carried out during the construction of the authorised scheme. The survey proposals must specify each survey’s objectives and explain how it will assist in either informing a useful and valid comparison with the pre-construction position and/or will enable the validation or otherwise of key predictions in the environmental statement.

(2)

The undertaker must carry out the surveys approved under sub-paragraph (1), and provide the agreed reports in the agreed format in accordance with the agreed timetable, unless otherwise agreed in writing with the MMO in consultation with the relevant statutory nature conservation bodies.

(3)

The undertaker must carry out the surveys specified in the construction monitoring plan in accordance with that plan, unless otherwise agreed in writing by the MMO in consultation with the relevant statutory nature conservation body.

(4)

All monitoring reports must be made publicly available and submitted to relevant evidence databases (as agreed with the MMO) no later than six months following written approval of the relevant report by the MMO under this condition, unless otherwise agreed in writing by the MMO.