Paragraph 2
No offshore works within the Dogger Bank SAC are to commence until—
the undertaker has received confirmation from the MRFO that the strategic compensation measure or other suitable measures are available to provide compensation for the AEoI;
the Marine Recovery Fund Payment has been quantified and the undertaker has entered into a contract to make a Marine Recovery Fund Payment;
an implementation and monitoring plan has been submitted to and approved by the Secretary of State; and
the full payment or the first payment in a series of instalments in accordance with the contract under sub-paragraph (b) has been made by the undertaker and the Secretary of State has confirmed in writing that such payment fulfils the requirement for compensation measures under this Part of this Schedule.