OpenLegislation

Paragraph 34 Amendments to approved details

Original text. Later amendments are not shown.

(1)

Where any requirement requires the authorised project to be carried out in accordance with the details approved by the relevant planning authority or another person (the “approving authority”), the approved details must be taken to include any amendments that may subsequently be approved by the approving authority (after consulting any person that the approving authority is required to consult under the relevant requirement).

(2)

The approving authority must not approve an amendment unless it is satisfied that the amendment is unlikely to give rise to any materially new or materially different environmental effects from those assessed in the environmental statement.