Paragraph 39 Applications made under requirements

Original text. Later amendments are not shown.

(1)

Where an application has been made to the discharging authority for any consent, agreement or approval required pursuant to a requirement included in Part 1 of this Schedule, or for any consent, agreement or approval further to any document referred to in any such requirement, the discharging authority must give notice to the undertaker of its decision on the application within a period of eight weeks beginning with—

(a)

the day immediately following that on which a valid application is received by the discharging authority (such validity to be confirmed by the discharging authority within five days of receipt of the application);

(b)

where further information is requested under paragraph 40, the day immediately following that on which the further information has been supplied by the undertaker; or

(c)

such longer period as may be agreed in writing by the undertaker and the discharging authority.

(2)

In determining any application made to the discharging authority for any consent, agreement or approval required by a requirement contained in Part 1 of this Schedule, the discharging authority may—

(a)

give or refuse its consent, agreement or approval; or

(b)

give its consent, agreement or approval either subject to reasonable conditions, or unconditionally,

  • and where consent, agreement or approval is refused or granted subject to conditions the discharging authority must provide its reasons for that decision within the notice of the decision.

(3)

In the event that the discharging authority does not determine an application within the period set out in sub-paragraph (1), the discharging authority is to be taken to have granted all parts of the application (without any condition or qualification) at the end of that period.

(4)

In this Part of this Schedule, references to the “undertaker” should be read as a reference to the undertaker who submitted the relevant application.